Articles / 4 min read
Sindh coal for Punjab buyers: Lakhra, Jhimpir and Khanot coal and what it costs to truck
Sindh coal from Lakhra, Jhimpir and Khanot is lignite, a lower-heat, wetter fuel than Duki or Chamalang, and it pays only for some Punjab buyers. We also supply it from the mines near Hyderabad. Below is how it compares and what a truck costs to move into Punjab, using a real freight rate card.

What the coal is
Lakhra lies about 16 km west of Khanot railway station on the Kotri to Dadu line, and its coal goes mainly to the Khanote power plant and to brick kilns. Dawn describes it as holding about 30% moisture in the ground, coming out in large lumps that crumble in open air, and prone to catch fire on its own in a pile.
The USGS puts the apparent rank of the southern Sindh coals between lignite A and sub-bituminous C. Jhimpir coal comes from the neighbouring Meting and Jhimpir field; we have found no published heat, ash or sulphur averages for it we can quote, so rely on a lab report for the lot.
| Coal | Heat (kcal/kg) | Moisture % | Ash % | Sulphur % |
|---|---|---|---|---|
| Lakhra, USGS average as received | 3,660 | 28.4 | 18.3 | 4.7 |
| Duki lump (our sheet) | 6,000 | 7 | 15 | 4.5 |
| Duki run-of-mine (our sheet) | 5,500 | 8 | 20 | 5 |
| Coal fines (our sheet) | 5,000 | 9 | 25 | 5 |
Who it suits
Buyers whose furnace is forgiving and who have a reason to want it. Lignite has been burned in fluidised bed boilers, built for wet high-sulphur fuel, and in brick kilns near the mine. A Punjab bhatta, a lime kiln or a boiler whose bed tolerates moisture can take it if the price per unit of heat justifies it. It does not suit a foundry cupola, a steel reheating furnace or a cement kiln burning to a tight recipe; for those we point buyers to Chamalang, Sor Range or Duki lump.
Sulphur and ash end up in the flue gas and the waste pile, and a fuel at the high end of the sulphur range is hard to defend if an inspector stops at a kiln gate in smog season. Ask for the sulphur figure before ordering, and keep Sindh coal piles low and spread, away from walls, with the oldest stock burned first.

Truck freight into Punjab
A Hyderabad goods transport company sent its rate card on 19 September 2026. Rates are per tonne from Khanot, Jhimpir is Rs 500 a tonne more, and trucks are priced at 24, 30 and 33 tonnes. These are the transporter's rates for the road only. They do not include the coal, loading at the mine or waiting charges.
| Destination | Rs per tonne from Khanot | Rs per tonne from Jhimpir | 24 t truck | 30 t truck | 33 t truck |
|---|---|---|---|---|---|
| Sadiqabad | 8,300 | 8,800 | 199,200 | 249,000 | 273,900 |
| Rahim Yar Khan area | 8,450 | 8,950 | 202,800 | 253,500 | 278,850 |
| Lodhran | 10,100 | 10,600 | 242,400 | 303,000 | 333,300 |
| Multan | 10,200 | 10,700 | 244,800 | 306,000 | 336,600 |
| Kacha Khoh | 10,750 | 11,250 | 258,000 | 322,500 | 354,750 |
| Vehari | 11,000 | 11,500 | 264,000 | 330,000 | 363,000 |
| Sahiwal | 11,500 | 12,000 | 276,000 | 345,000 | 379,500 |
| Okara | 11,850 | 12,350 | 284,400 | 355,500 | 391,050 |
| Pattoki | 12,400 | 12,900 | 297,600 | 372,000 | 409,200 |
| Lahore | 13,100 | 13,600 | 314,400 | 393,000 | 432,300 |
| Sheikhupura | 13,200 | 13,700 | 316,800 | 396,000 | 435,600 |
| Gujranwala and Sialkot | 13,600 | 14,100 | 326,400 | 408,000 | 448,800 |
| Khushab | 13,800 | 14,300 | 331,200 | 414,000 | 455,400 |
Freight on lower-heat coal
The road charges by the tonne and you burn heat. A tonne of Duki lump holds about 6 million kcal and a tonne of Lakhra coal about 3.7 million, so the same Rs 13,100 to Lahore buys much less heat on lignite: about Rs 3,579 per million kcal in freight alone. The sheet gap between ex-Quetta and delivered for Duki lump is Rs 13,000 a tonne, about Rs 2,167 per million kcal, though that gap covers more than road freight.
To compare, add the mine price, freight and loading to get a gate price, divide by the lab heat in kcal/kg over 1,000, and do the same for the delivered Balochistan price. Our delivered Duki lump costs about Rs 8,625 per million kcal, so Sindh coal at 3,660 kcal/kg must land at Lahore under about Rs 31,568 a tonne to match, which is about Rs 18,468 at the mine after Rs 13,100 freight. That is arithmetic, not an offer, and it ignores extra ash, moisture and sulphur.
- Sadiqabad2,268 Rs per million kcal
- Multan2,787 Rs per million kcal
- Sahiwal3,142 Rs per million kcal
- Lahore3,579 Rs per million kcal
- Gujranwala and Sialkot3,716 Rs per million kcal
- Khushab3,770 Rs per million kcal
Freight per tonne divided by 3.66 (3,660 kcal/kg divided by 1,000). Source of rates: a Hyderabad goods transport rate card, 19 September 2026.
Questions people ask
Can I use Sindh coal in a brick kiln in Punjab?
Lignite is used in kilns, but Punjab is enforcing smog rules and the sulphur content matters. Get the lab sulphur figure and confirm the kiln meets the zigzag requirement before you buy.
What is the difference between Khanot and Jhimpir coal?
They come from different parts of the Sindh lignite belt. Loading at Jhimpir adds Rs 500 a tonne on the rate card we hold.
Prices are indicative, per tonne, excluding sales tax, and change week to week. See today's sheet or ask us for a confirmed price.