Gas load shedding in winter 2026 to 27 has no announced schedule yet, and a factory cannot wait for one. As of 28 October SNGPL has published nothing, so the useful number is how much coal your boiler would burn on the day the gas drops.

What last winter's plan looked like
For December 2025 to February 2026 SNGPL gave homes in Punjab and KP gas in three daily windows: 5:30 to 8:30 am, 11:30 am to 1:30 pm and 5:30 to 8:30 pm, eight hours of twenty-four. Officials said industry would not be cut. In earlier winters non-export industry was cut to keep homes supplied, so one year's statement is not a promise for the next.
Anyone sharing a new schedule on WhatsApp now is passing on last year's timings. A household that needs heat outside the windows should read the article on coal heater safety before lighting anything in a shut room.
Gas has already got dearer for factories
Under the IMF programme the gas price for captive power was raised and a grid levy added from March 2025, scheduled to climb in steps to about Rs 6,000 per mmBtu by August 2026. Even with full supply, many units now find coal cheaper for steam and heat. Check the grate, the feed system and the chimney before the first cut, because a boiler that has stood idle on gas needs a walk-round before it is asked to run for days.

How much coal replaces your gas
Take the gas you burn on a normal winter day, turn it into heat, and divide by the heat in the coal. One mmBtu is about 252,000 kcal; Duki lump gives about 6,000 kcal/kg. The chart assumes 85% efficiency on gas and 75% on coal, so substitute your own figures if you have them.
Keep enough for the gap between ordering and delivery plus a few days. A truck from Quetta takes 2 to 3 days on the road to Punjab, and loading can add one. Two weeks is a sensible floor for a plant that cannot stop. Our minimum order is 25 tonnes, so the smaller rows are one truck at a time.
- 25 mmBtu of gas a day1.2 tonnes a day
- 50 mmBtu of gas a day2.4 tonnes a day
- 100 mmBtu of gas a day4.8 tonnes a day
- 200 mmBtu of gas a day9.5 tonnes a day
Tonnes a day = mmBtu x 252,000 kcal x (0.85 / 0.75) divided by 6,000,000 kcal per tonne. Fourteen days of stock is the daily figure times 14.
Ash, order timing and price
A tonne of coal at 15% ash leaves about 150 kg, so a boiler on five tonnes a day makes three quarters of a tonne of ash every day that someone has to rake, wet and cart away. The article on coal ash covers where it can go.
Delivered to Punjab, Duki lump is Rs 51,750 a tonne, Sor Range Rs 52,250 and fines Rs 38,000, confirmed when you contact us. Order in November. When many plants switch in the same week, trucks get scarce and loading queues grow.
Questions people ask
Will industry get gas this winter?
Nothing has been announced. Last winter officials said industry would not be cut, but non-export industry was cut in earlier winters to protect home supply. Plan a backup fuel to be safe.
Can a gas boiler burn coal without changes?
No. A gas burner cannot take coal; the grate, feeder and ash handling have to be fitted. Our article on switching a boiler from gas to coal covers the work.
Prices are indicative, per tonne, excluding sales tax, and change week to week. See today's sheet or ask us for a confirmed price.